Sample U.S. projects under development by Solariant Capital

New River Solar

Bradford County, Florida

74.9 MW Solar + 70 MW

  • Development Status: Site Control executed, Interconnection System Impact Study in progress, Critical Issues Analysis Complete.
  • Expected Commercial Operation Date NTP: September 2025, COD: September 2026

Pleasant Solar

Alachua County, Florida

74.9MW Solar + 70 MW

  • Development Status: Site Control Secured, LGIA Executed & Suspended, Starting City Site Plan & Special Exception Permitting.
  • Expected Commercial Operation Date NTP: July 2025, COD: June 2026

Racetrack Solar

Alachua County, Florida

74.9 MW Solar + 70 MW

  • Development Status: Site Control executed, GRU accepted IR, Initial Permitting & Environmental site work started.
  • 2025 NTP: June 2026, COD: June 2027

Wakulla Solar

Wakulla County, Florida

74.9 MW Solar + 70 MW

  • Development Status: Site Control executed, Interconnection Request Submitted & studies in process, Critical Issues Analysis & Phase 1 ESA Complete.
  • Expected Commercial Operation Date NTP: December 2025, COD: December 2026

Canoochee River Solar

Emanuel County, Georgia

150 MW Solar + 45 MW

  • Development Status: Site Control executed, Interconnection Request submitted, Critical Issues Analysis & Phase 1 ESA in progress.
  • Expected Commercial Operation Date NTP: November 2027,COD: November 2028

Red Dirt Solar

Talbot County, Georgia

150MW Solar + 75MW/300MWh Storage

  • Development Status: Site Control Option Executed, System Impact Study in process, Critical Issues Analysis completed, Phase I ESA completed.
  • Expected Commercial Operation Date NTP: November 2027, COD: November 2028

Southern Sky Solar

Clinch County, Georgia

100 MW Solar + 50 MW

  • Development Status: Site Control executed, System Impact Study in Process, Critical Issues Analysis complete & Phase I ESA completed.
  • Expected Commercial Operation Date NTD: September 2027, COD: September 2028

Two Rivers Solar

Camden County, Georgia

100 MW Solar + 50 MW

  • Development Status: Site Control executed, Interconnection System Impact Study Completed, Facilities Study in progress, Critical Issues Analysis and Phase 1 ESA complete.
  • Expected Commercial Operation Date NTP: April 2026, COD: September 2027

Rochester Road Solar

Butler County, Kentucky

115 MW Solar + 50 MW / 200 MWh Storage

  • Development Status: Site Control executed, System Impact Study in Progress, Critical Issues Analysis Completed.
  • Expected Commercial Operation Date NTP: November 2025, COD: November 2026